Engineers say design flaws delay Shek Kwu Chau incinerator tenders

Despite the apparent urgency to start work on the HK$19.2 billion incinerator project at Shek Kwu Chau, contractors are wondering why it is taking so long for the Environmental Protection Department (EDP) to release the tender documents. In an announcement on December 20 last year, four companies were prequalified to bid for the Integrated Waste Management Facility (IWMF) but four months later they are still waiting to see the tender documents. One consultant familiar with the project said, “The tender documents should have been ready by now particularly as the project has been held up by judicial challenges for two and a half years.” HowardWinnReports understands that one possible reason why the tender documents have not been sent out is the emergence of a problem with the proposed construction method for the artificial island which is to house the iWMF. Continue reading